Grandview Heights Power System Upgrades


A Power System Upgrade for the Grandview Heights Community began in May 2010, in order to continue to provide safe and reliable power service to residents in the neighbourhood. It is expected that all upgrades will be completed by Fall 2011.


The Power System Upgrade involves the replacement of underground cable and placement of new transformers (3ft by 3ft boxes) above ground on public lands adjacent to residential properties in the community. The replacement of underground cable will require some trenching and directional drilling that may temporarily disturb some paved and landscaped areas in the neighbourhood.


Transformers, which are the standard for newer neighbourhoods in the city, replace the underground vaults that are currently in use in this neighbourhood. This allows for easier access to the system and reduces service repair time. Once construction is completed, EPCOR will restore any areas impacted by construction activity.


The goal of the project is to conduct all work in a safe and efficient manner and to mitigate, where possible, impacts to residents living in the area.

 
Open House
 

EPCOR hosted an Open House on Wednesday April 20, 2011 from 2:30 to 6:30 pm at Grandview Heights Community Centre (12603-63 Avenue).  It was an opportunity to ask questions, provide feedback and learn about upcoming construction in the community and locations of Phase III transformer pads.

View the Open House poster boards.


Construction Updates

Phase I - construction is now complete.


Phase II - Construction has begun.

 

Phase III - Construction is expected to begin this summer.


Locations* for Transformer Pads in Phase 2

  • Transformer 1: 13103 Grandview Drive
  • Transformer 2: 12707 Grandview Drive
  • Transformer 3: 12504-66 Ave
  • Transformer 4: In front of 6515 Grandview Drive
  • Transformer 5: In front of 6503-132 Street
  • Transformer 6: Between 12908-66 Avenue and 13004-66 Avenue

*All transformer pads are located on public lands adjacent to these properties.


Phase III

Locations* for Transformer Pads in Phase 3

  • Transformer 1: 12432 Grandview Drive (existing pad, transformer will be replaced)
  • Transformer 2: 12407-12405 Grandview Drive (new transformer)
  • Transformer 3: 12307-12303 Grandview Drive (new transformer)
  • Transformer 4: 12303 66 Ave - 6612 123 Street (new transformer)
  • Transformer 5: Green space island across from 6613 124 Street (new transformer)
  • Transformer 6: 12311-12307 65 Avenue (existing pad, transformer will be replaced)
  • Transformer 7: 12303 65 Avenue (new transformer)
  • Transformer 8: 12306 63 Avenue (part of the strip mall, transformer to be rebuilt)
  • Transformer 9: 6403 132 Street
  • Transformer 10: 6308 131 Street
  • Transformer 11: 12920 63 Avenue
  • Transformer 12: Green space island across from 12916 65 Avenue
  • Transformer 13: Green space island across from 12903 64 Avenue
  • Transformer 14: 6303 128 Street
  • Transformer 15: 6304 126 Street
  • Transformer 16: Green space island across from 6503 126 Street and 12603 65 Avenue
  • Transformer 17: Green space island across from 6507 126 Street and 12604 66 Avenue
  • Transformer 18: 6304 125 Street
  • Transformer 19: 6233 63 Avenue

*All transformer pads are located on public lands adjacent to these properties.
There may be additions or modifications to the transformer locations.